View a PDF version of this week's update
600 W. 125th Street
Current Phase of Construction: Curtainwall and Interior Fit-Out
- Noisy work should be expected during most days during this phase of construction.
- The curtain wall contractor will install soffit and western exterior walls from inside the new building using small lifts and cranes as well as exterior lifts and scaffolding.
- This phase is anticipated to be complete in August 2024, weather permitting.
What is Happening During the Next Two Weeks:
- Utilities and the fire alarm system are being installed and inspected throughout the building.
- The building enclosure contractor is completing the installation of exterior panels.
- Layout and installation of interior walls by carpenter.
- Installation of flooring, terrace pavers, kitchen cabinets, millwork, tiling, and painting is in progress.
Studebaker Building Façade Repairs and Roof Replacement
- The facade project will resume the week of August 26. The terracotta installation at the ground level will commence at both street elevations. Expect medium to high levels of intermittent drilling noise. This noise will be more noticeable on the lower floors.
- The estimated completion is October 2024.
Please note that all activities are subject to change based on weather and other field conditions.