View a PDF version of this week's update
Site at 125th Street and 12th Avenue
- Importing clean fill and topsoil to grade the site to meet new elevations
- Pouring concrete at new sidewalk at 125th Street and concrete walkways
- Demolition, excavation, and off-loading soil offsite
- Commencing the installation of the new site perimeter fence
- Soil compaction and testing is ongoing
- Installation of the new light pole bases
- Installation of irrigation system piping
- Integrated pest control sitewide
-Please note that all activities are subject to change based on weather and other field conditions-