600 W. 125th Street
Current Phase of Construction: Curtainwall and Interior Fit-Out
- Noisy work should be expected during most days during this phase of construction.
- The curtainwall contractor will install exterior walls from inside the new building using small lifts and cranes as well as exterior scaffolding.
- This phase is anticipated to be complete in Spring 2024.
What is Happening During the Next Two Weeks:
- Street work for telecommunications service on 125th Street. Manholes will be opened to pull cables on Broadway and 125th Street.
- Utilities and the fire alarm system are being installed throughout the building.
- Elevator installation is substantially complete.
- Exterior vertical transportation is being disassembled.
- The building enclosure contractor is completing deliveries and installing exterior panels.
- Layout and installation of interior walls by masons and carpenter.
- Small pump trucks will be used to install finished concrete floors.
- Installation of flooring, kitchen cabinets, millwork, tiling, and painting is in progress.
Studebaker Building Façade Repairs and Roof Replacement
- The terra cotta installation at the ground level will commence at both street elevations. This work continues until the project's completion, estimated for June 2024. Expect medium to high levels of intermittent drilling noise. This noise will be more noticeable on the lower floors.
Please note that all activities are subject to change based on weather and other field conditions.