View a PDF version of this week's update
600 W. 125th Street
Current Phase of Construction: Superstructure:
- Noisy work should be expected during most days during this phase of construction
- The superstructure phase is anticipated to be complete in Spring 2023
What is Happening During the Next Two Weeks:
- Installation of adjacent building rooftop protection
- Daytime utility work on 125th Street by Con Edison is nearing completion for temporary power
- New building utilities are being coordinated and installed
- Delivery and installation of rebar and formwork for columns and third and fourth floor slabs. Concrete trucks and pumps will be used to pour columns and slabs.
- Hoist and loading dock installation
- Support of excavation removal from the cellar will commence and there may be some visible smoke that contractors will control using air filtration equipment and fans
- Regular work hours temporarily extended until 8:00 p.m., Monday through Friday
Studebaker Building Façade Repairs and Roof Replacement
- Parapet rebuilding will continue for the remainder of the calendar year. Work is mostly quiet.
- On the south elevation, window caulking replacement, lintel painting, and corrective brick repointing will begin. Joint cutting and caulking removal will create intermittent grinding noise and dust for the first week and then the work will be mostly quiet. Work areas will be accessed via hanging scaffolding.
- Terra cotta repairs will continue at the west parapet wall. Work is mostly quiet but occasional drilling is expected.
Please note that all activities are subject to change based on weather and other field conditions.