600 W. 125th Street

Current Phase of Construction: Curtainwall and Interior Fit-Out

  • Noisy work should be expected during most days during this phase of construction.
  • The curtainwall contractor will install exterior walls from inside the new building using small lifts and cranes as well as exterior scaffolding.
  • This phase is anticipated to be complete in Spring 2024.

What is Happening During the Next Two Weeks:

  • Overnight street work for telecommunications service on 125th Street is anticipated to commence on or around Wednesday, January 24, pending necessary approvals. Work is expected to occur between 10:00 p.m. to 4:00 a.m. and will involve saw cutting to open up the street, a small excavator to trench the opening, the installation of conduits, backfill, and the repair of the road. This work is anticipated to take one week to complete.
  • Utilities and fire alarm system are being installed throughout the building.
  • Elevator installation is nearing completion.
  • The building enclosure contractor is completing deliveries and installing exterior panels.
  • Layout and installation of interior walls by masons and carpenter.
  • Small pump trucks will be used to install finished concrete floors.
  • Installation of flooring, kitchen cabinets, millwork, tiling, and painting is in progress.

Studebaker Building Façade Repairs and Roof Replacement

  • Lintel and miscellaneous masonry repair work will continue at the west elevation (north of elevator tower). Due to inclement weather, this work has been delayed for another week. Expect a medium to high level of occasional drilling and cutting noises on all floors.
  • Terra cotta installation will continue at the elevator tower until the end of January 2024. Any noise and dust from this area will be unnoticeable to occupants.
  • The next expected noisy work will start on or around mid-February 2024, which includes roof replacement around the elevator tower and terra cotta installation at the ground level.

 

Please note that all activities are subject to change based on weather and other field conditions.

 


 

    What to Expect

    • Regular working hours are 7:00 a.m. to 6:00 p.m. Monday to Friday. Some work may also be performed after hours and on weekends from 8:00 a.m. to 5:00 p.m. in accordance with all necessary permits. After-hours permit approved for 6:30 a.m. operation of the hoist to transport workers to floors where work is being performed. This permit is required as a safety precaution to reduce overcrowding as well as to help mitigate noise at the loading dock.
    • Work hours for overnight utility street work are 10:00 p.m. to 4:00 a.m. Monday through Friday, with possible work hours on Saturday and Sunday in accordance with all necessary permits by the NYC Department of Transportation. 
    • Note that the contractor will begin daily set-up preparations 30 to 60 minutes before work commences and will perform site clean-up 30 to 60 minutes after work is completed.
    • Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur.
    • Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. Visit the project page to learn about our comprehensive clean construction program and mitigation protocols.
    • The parking lane will be closed on the south side of W. 125th Street from Broadway to St. Clair Place. Parking will not be available on the south side of W. 125th Street from Broadway to the mid-block in front of the entire length of the 600 W. 125th Street construction fence.
    • Refer to street signage for the west side of Broadway from 129th to 130th Streets — parking is allowed from 7:00 p.m. to 2:00 a.m., and on weekends.