600 W. 125th Street
Current Phase of Construction: Excavation and Foundation:
- Noisy work should be expected during most days during this phase of construction
- Excavation and foundation is anticipated to be complete by mid-October 2022
- The superstructure contractor is anticipated to gradually begin working on site starting the week of October 17
What is Happening During the Next Two Weeks:
- Daytime utility work on Broadway has commenced. Work will involve the contractor saw cutting and breaking up the street and sidewalk to install the new building utility connections (for future water and sanitary) by using jackhammers, road saw, and backhoe. A dump truck will be used to remove material.
- Installation of foundation wall formwork and rebar, waterproofing, and steel bracing
- Concrete trucks will be used to install foundation walls
- Installation of cellar curbs and tower crane pad
- An excavator will be used to complete cleanup and backfill
- The superstructure contractor will begin mobilization the week of October 17
- Installation of sidewalk protection and rooftop protection at adjacent buildings. In addition, protection for the 125th Street subway station escalator will start the week of October 10, from 11:00 p.m. to 7:00 a.m.
- Regular work hours temporarily extended until 8:00 p.m., Monday through Friday
Studebaker Building Façade Repairs and Roof Replacement
- Terra cotta repairs will continue at the north parapet wall. Intermittent drilling and dust are expected, mainly on the 6th floor
- Selective areas of terra cotta, concrete and brick piers will be demolished at the west parapet wall. Intermittent drilling, grinding noise and dust are expected mainly on the 6th floor.
Please note that all activities are subject to change based on weather and other field conditions.