Construction Update: Weeks of 8/17/26 and 8/24/26

August 14, 2026

View a PDF version of this week's update

Site at 125th Street and 12th Avenue

  • Integrated pest control sitewide
  • Mobilization of heavy equipment and sound testing on all machinery to meet acoustical requirements
  • Surveying for different soil types
  • Commencing trenching activities for soil remediation

-Please note that all activities are subject to change based on weather and other field conditions-

 


What to Expect

  • Work hours are 7:00 a.m. to 3:30 p.m., Monday to Friday.
  • Expect noise, delivery of materials, and other impacts typically associated with construction projects.