Site at 125th Street and 12th Avenue
- Importing clean fill and topsoil to grade the site to meet new elevations
- Installing new sidewalk at 125th Street and 20-foot concrete walkway
- Planting trees and shrubs on the east planting area
- Commencing the installation of the new site perimeter fence
- Soil compaction and testing is ongoing
- Running conduits and piping for the new light poles
- Installing piping for the irrigation system
- Integrated pest control sitewide
-Please note that all activities are subject to change based on weather and other field conditions-