What is Happening
Columbia Business School
Site 7 (Western Site)
- Completion of exterior wall glass-fiber reinforced concrete unit installations are ongoing on levels 4 through 11
- Exterior wall glass installation is ongoing on level 1, north and south facades
- Riser ductwork and pipe installation is ongoing
- Roof ductwork re-routing/support steel
- Interior fit-outs and overhead mechanical, electrical, and plumbing installation is ongoing on levels 1 through 11
- Finishes program is in progress on levels 3 through 7
- Elevator work on platforms, counterweights at north and south banks are ongoing
Site 6B (Eastern Site)
- Completion of exterior wall glass-fiber reinforced concrete unit installations are ongoing on levels 2 through 8
- Exterior wall glass installation is ongoing on level 1, north and south facades
- Fin tube radiator installation on the west façade
- Mechanical, electrical, and plumbing system work under the Forum space is ongoing
- Smoke baffle installation along the network stairs
- Elevator work on platforms and counterweights for south cars, and rail stacking in north bank
- Roof perimeter guardrail installation
- Interior fit-outs and overhead mechanical, electrical, and plumbing installation is ongoing on levels 2 through 8
- Riser ductwork and pipe installation is ongoing
Below Grade Activity / W. 131st Street Utilities
- Installation of storm, sanitary piping, electrical conduits, low voltage and HVAC ductwork is ongoing
- Buildout work including metal panel installation of the loading dock is progressing
- Wall framing and sheetrock work are ongoing throughout
- Waterproofing of the sump pits is ongoing
Open Spaces between 130th and 131st Streets and along 12th Avenue
- Inner and outer ring formwork, reinforcement, and concrete placement is ongoing
- Perimeter trench drain development
- Electrical sleeve installation
W. 125th Street South Side Demolition
Please note that all activities are subject to change based on weather and other field conditions.
What to Expect
Construction Activity
- Regular weekday work hours: 7:00 a.m. to 6:00 p.m. Saturday and Sunday work hours: 7:00 a.m. to 5:00 p.m. After-hours permit issued for 6:00 a.m. construction start to allow for physical distancing for workers upon entry to the site.
- Material deliveries to site is ongoing
Temporary Traffic and Transportation Impacts