View a PDF version of this week's update
600 W. 125th Street
Current Phase of Construction: Curtainwall and Interior Fit-Out
- Noisy work should be expected during most days during this phase of construction.
- Curtainwall phase is substantially complete and removal of hanging scaffold will begin.
What is Happening During the Next Two Weeks:
- Installation of flooring, terrace pavers, kitchen cabinets, millwork, tiling, finishing drywall and painting is in progress on upper floors.
- First phase of tenants will begin moving into the building.
- Protection at 125th Street will begin to be removed.
Studebaker Building Façade Repairs and Roof Replacement
- The terracotta installation at the ground level will continue at both street elevations. Expect medium to high levels of intermittent drilling noise. This noise will be more noticeable on the lower floors.
- The estimated completion is October 2024.
Please note that all activities are subject to change based on weather and other field conditions.