View a PDF version of this week's update
600 W. 125th Street
Current Phase of Construction: Curtainwall and Interior Fit-Out
- Noisy work should be expected during most days during this phase of construction.
- The curtain wall contractor will install soffit and western exterior walls from inside the new building using small lifts and cranes as well as exterior lifts and scaffolding.
- This phase is anticipated to be complete in Summer 2024.
What is Happening During the Next Two Weeks:
- Utilities and the fire alarm system are being installed and inspected throughout the building.
- The building enclosure contractor is completing the installation of exterior panels.
- Layout and installation of interior walls by carpenter.
- Small pump trucks will be used to install finished concrete floors.
- Installation of flooring, terrace pavers, kitchen cabinets, millwork, tiling, and painting is in progress.
Studebaker Building Façade Repairs and Roof Replacement
- The facade project is on hold while the contractor waits for additional stone units to arrive. The work will resume when the last of the remaining shipments is delivered around mid-July.
- The estimated completion is still August 2024.
Please note that all activities are subject to change based on weather and other field conditions.