600 W. 125th Street
Current Phase of Construction: Grading Adjacent Lot and Punchlist
- Noisy work should be expected during most days during this phase of construction.
- This phase is anticipated to be complete by mid-May 2025.
What is Happening During the Next Two Weeks:
- Installing a new sidewalk along Broadway, Monday-Friday from 9:00 a.m. to 4:00 p.m., Saturday from 8:00 a.m. to 6:00 p.m., and Sunday from 9:00 a.m. to 6:00 p.m. Work will be coordinated to minimize impacts to pedestrians and subway riders.
Please note that all activities are subject to change based on weather and other field conditions.