View a PDF version of this week's update
600 W. 125th Street
Current Phase of Construction: Grading Adjacent Lot and Punchlist
- Noisy work should be expected during most days during this phase of construction.
- This phase is anticipated to be complete by mid-May 2025.
What is Happening During the Next Two Weeks:
- Installation of a new sidewalk along Broadway and 125th Street. Work will take place Monday to Friday from 9:00 a.m. to 4:00 p.m., Saturday from 8:00 a.m. to 6:00 p.m. and Sunday from 9:00 a.m. to 6:00 p.m. Work will be coordinated to minimize impacts to pedestrians and subway riders.
- Landscaping will be completed next to the front entrance
Please note that all activities are subject to change based on weather and other field conditions.