View a PDF version of this week's update
600 W. 125th Street
Current Phase of Construction: Grading Adjacent Lot and Punchlist
- Noisy work should be expected during most days during this phase of construction.
- This phase is anticipated to be complete by the end of April 2025.
What is Happening During the Next Two Weeks:
- Overnight work to install a new sidewalk along Broadway in front of 600 W. 125th Street anticipated to start in mid-April, pending necessary approvals. The MTA requires this work to take place during the overnight hours to minimize impacts to pedestrians and subway riders.
- Finishing drywall and painting on upper floors.
- McDonald’s will have their grand opening on Wednesday, April 9.
Please note that all activities are subject to change based on weather and other field conditions.