View a PDF version of this week's update
What is Happening
Columbia Business School
Site 7 (Western Site)
- Elevator trade has mobilized to site
- Plumbing and ductwork are in progress up to roof level
- Curtain wall installation is in progress on levels 3 through 11
- Urban layer glass is in progress
- Interior wall layout and framing is in progress up to level 10
- Overhead mechanicals is ongoing
- Rooftop equipment will be picked and set
Site 6B (Eastern Site)
Below Grade Activity / W. 131st Street Utilities
- Domestic water, sanitary, and storm-piping is ongoing at all levels
- HVAC piping work is ongoing in sub-cellar levels 1 and 3; chilled water main and high-pressure steam piping in the utility tunnel are progressing to completion
- Air handling units at sub-cellar level 1 and W. 130th Street energy transfer room equipment are being hooked up with piping and ductwork
- Sprinkler system installation is in progress
- Fire alarm system installation is in progress
- Installation of masonry walls at ramp and sub-cellar level 3
- Top down wall construction on sub-cellar levels 1 and 2
- Concrete placement for equipment pads is ongoing
- The W. 130th Street energy transfer room equipment installation is ongoing
- Sheet metal ductwork in sub-cellar level 1 of Site 7 and Site 6B, and sub-cellar level 3 of W. 130th Street
- Ductwork risers are ongoing in mechanical shafts in Site 7 and 6B
- L1 Plaza drainage, waterproofing, and topping slab development work is on-going
- Block filler and floor sealant is ongoing
W. 125th Street South Side Demolition
- Third submission of demolition plans was sent to NYC Department of Buildings
- Mechanical, electrical, and plumbing disconnects at the east wall at Prentis Hall and wall patching is ongoing. Fire standpipe and steam line is to be cut and cap on Wednesday, February 5.
- The condenser unit at the warehouse roof at 3191 Broadway was removed along with its associated piping and the indoor AC unit
Please note that all activities are subject to change based on weather and other field conditions.
What to Expect
Construction Activity
- Regular weekday work hours: 7:00 a.m. to 6:00 p.m. Saturday and Sunday work hours: 7:00 a.m. to 5:00 p.m.
- Material deliveries to site is ongoing
Temporary Traffic and Transportation Impacts
- Refer to street signage for the west side of Broadway from 129th to 130th Streets -- parking is allowed after 6:00 p.m. and on weekends
- W. 131st Street between Broadway and 12th Ave. is opened for one-way westbound traffic