600 W. 125th Street
Current Phase of Construction: Grading Adjacent Lot and Punchlist
- Noisy work should be expected during most days during this phase of construction.
- This phase is anticipated to be complete by the end of the first quarter of 2025.
What is Happening During the Next Two Weeks:
- Finishing drywall and painting on upper floors
- Removal of protection at neighboring buildings
- Grading and installing drainage at adjacent empty lot
- McDonald’s is constructing their new restaurant space on the ground floor
Please note that all activities are subject to change based on weather and other field conditions.