Construction Update: Weeks of 12/9/24 and 12/16/24

The latest updates on what to expect and construction updates related to the Manhattanville campus.

December 06, 2024

View a PDF version of this week's update

600 W. 125th Street

Current Phase of Construction: Interior Fit-Out

  • Noisy work should be expected during most days during this phase of construction.
  • This phase is anticipated to be complete in winter 2024.

What is Happening During the Next Two Weeks:

  • Finishing drywall and painting is in progress on upper floors.
  • The first phase of tenants is moving into the building.
  • Removal of protection at neighboring buildings and along Broadway.
  • Grading staging construction lot.
     

Studebaker Building Façade Repairs and Roof Replacement

  • Façade repairs are complete. 
  • Window washing at the north and south elevations.
  • Temporary lighting to be installed at the ground floor level at the north and south elevations.

Please note that all activities are subject to change based on weather and other field conditions.

 


 

    What to Expect

    • Working hours are 7:00 a.m. to 8:00 p.m. Monday to Friday. Some work may also be performed after hours and on weekends from 9:00 a.m. to 5:00 p.m. in accordance with all necessary permits.
    • Note that the contractor will begin daily set-up preparations 30 to 60 minutes before work commences and will perform site clean-up 30 to 60 minutes after work is completed.
    • Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur.
    • Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. Visit the project page to learn about our comprehensive clean construction program and mitigation protocols.
    • The parking lane will be closed on the south side of W. 125th Street from Broadway to St. Clair Place. Parking will not be available on the south side of W. 125th Street from Broadway to the mid-block in front of the entire length of the 600 W. 125th Street construction fence.
    • Refer to street signage for the west side of Broadway from 129th to 130th Streets — parking is allowed from 7:00 p.m. to 2:00 a.m., and on weekends.