View a PDF version of this week's update
600 W. 125th Street
Current Phase of Construction: Grading Adjacent Lot and Punchlist
- Noisy work should be expected during most days during this phase of construction.
- This phase is anticipated to be complete by the end of the first quarter of 2025.
What is Happening During the Next Two Weeks:
- Overnight work to install a new sidewalk along Broadway in front of 600 W. 125th Street anticipated during the week of January 13, pending necessary approvals. The MTA requires this work to take place during the overnight hours to minimize impacts to pedestrians and subway riders.
- Finishing drywall and painting on upper floors
- Removal of protection at neighboring buildings
- Grading and installation of drainage at adjacent empty lot
- McDonald’s is constructing their new restaurant space on the ground floor
Please note that all activities are subject to change based on weather and other field conditions.