600 W. 125th Street
Current Phase of Construction: Interior Fit-Out
- Noisy work should be expected during most days during this phase of construction.
- This phase is anticipated to be complete in winter 2024.
What is Happening During the Next Two Weeks:
- Installation of flooring, terrace pavers and planters, kitchen cabinets, millwork, tiling, finishing drywall, and painting is in progress on upper floors.
- The first phase of tenants is moving into the building.
- Sidewalk installation along 125th Street has commenced.
- Removal of protection at neighboring buildings and along Broadway in mid-November.
Studebaker Building Façade Repairs and Roof Replacement
- Façade repairs are complete; only minor repairs remain at the north egress doors.
- Window washing will continue for the next three weeks at the north and south elevations.
Please note that all activities are subject to change based on weather and other field conditions.