Construction Update: Weeks of 10/21/24 and 10/28/24

The latest updates on what to expect and construction updates related to the Manhattanville campus.

October 18, 2024

View a PDF version of this week's update

600 W. 125th Street

Current Phase of Construction: Interior Fit-Out

  • Noisy work should be expected during most days during this phase of construction.
  • Curtainwall phase is substantially complete and removal of hanging scaffold is in progress.
  • This phase is anticipated to be complete in winter 2024.

What is Happening During the Next Two Weeks:

  • Installation of flooring, terrace pavers, kitchen cabinets, millwork, tiling, finishing drywall and painting is in progress on upper floors.
  • Installation of exterior panels on the terrace and roof walls.
  • The first phase of tenants is moving into the building.
  • Protection at 125th Street will begin to be removed at the end of October or early November, pending necessary approvals.

Studebaker Building Façade Repairs and Roof Replacement

  • The terracotta installation at the ground level will continue at both street elevations. Expect medium to high levels of intermittent drilling noise. This noise will be more noticeable on the lower floors. 
  • The estimated completion is early November 2024.

Please note that all activities are subject to change based on weather and other field conditions.

 


 

    What to Expect

    • Working hours are 7:00 a.m. to 8:00 p.m. Monday to Friday. Some work may also be performed after hours and on weekends from 9:00 a.m. to 5:00 p.m. in accordance with all necessary permits.
    • Note that the contractor will begin daily set-up preparations 30 to 60 minutes before work commences and will perform site clean-up 30 to 60 minutes after work is completed.
    • Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur.
    • Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. Visit the project page to learn about our comprehensive clean construction program and mitigation protocols.
    • The parking lane will be closed on the south side of W. 125th Street from Broadway to St. Clair Place. Parking will not be available on the south side of W. 125th Street from Broadway to the mid-block in front of the entire length of the 600 W. 125th Street construction fence.
    • Refer to street signage for the west side of Broadway from 129th to 130th Streets — parking is allowed from 7:00 p.m. to 2:00 a.m., and on weekends.