Construction Update: Weeks of 10/21/19 and 10/28/19
October 18, 2019
View a PDF version of this week's update
What is Happening
The Forum
- Punchlist
Columbia Business School
Site 7 (Western Site)
- Concrete is installed up to the roof and elevator machine room
- Egress stair pours are in progress
- Plumbing and ductwork up to level 6
- Spray on fireproofing is up to level 11
- Curtain wall installation is partially up to level 7
- Interior wall installation up to level 5
Site 6B (Eastern Site)
- Concrete slab placed up to level 8
- Curtain wall curbs and anchor installation are up to level 5
- Spray on fireproofing is up to level 6
- Exterior east elevation framing for metal panels is up to level 4
- Interior wall layout is in progress
Below Grade Activity / W. 131st Street Utilities
- Street light work on W. 131st Street
- Road and sidewalk demolition and excavation on W. 131st Street
- Tying new sanitary lines and storm lines into the Studebaker Building
- Installing IT conduits on W. 131st Street
- Coring penetrations for laterals at the Studebaker Building
- Plumbing and sprinkler piping ongoing at sub cellar 1 and 3 levels
- Installation of chilled water supply and return, and high pressure steam main and condensate return piping installation in utility tunnel
- Installation of masonry walls, concrete curbs, and mechanical, electrical, and plumbing (MEP) pads at sub-cellar 1 and 3 levels
- Beam penetrations for CDS units (a unit that captures and treats stormwater runoff onsite before entering the city's sewer system)
- Overhead conduits and concrete structrual supports ongoing
- Tower crane slab in-fill
- MEP equipment rigging ongoing
- Site 6B and Site 7 loading dock development
- Insulation under side of ramp
- Masonry trade mobilizing
W. 132nd Street Demolition Project
- Clean up of debris of 3259 Broadway and hauling debris offsite
- Installing new site fence
W. 125th Street South Side Demolition
- Temporary power and light installation
- General cleaning
- Installing construction fence at warehouse
- Installing sidewalk bridge at warehouse and guard booth
Please note that all activities are subject to change based on weather and other field conditions.
What to Expect
Construction Activity
- Regular weekday work hours: 7:00 a.m. to 6:00 p.m. Saturday and Sunday work hours: 7:00 a.m. to 5:00 p.m.
- Material deliveries to site is ongoing
Temporary Traffic and Transportation Impacts
- Refer to street signage for the west side of Broadway from 129th to 130th Streets -- parking is allowed after 6:00 p.m. and on weekends