What is Happening

Columbia Business School

Site 7 (Western Site)

  • Completion of the exterior wall.  Cleaning, ongoing punchlist work, and water testing.
  • Interior finishes and punchlist ongoing
  • A/V work in classrooms
  • Delivery and installation of furniture ongoing

Site 6B (Eastern Site)

  • Completion of the exterior wall.  Cleaning, ongoing punchlist work, and water testing.
  • Interior finishes ongoing
  • A/V work in classrooms
  • Delivery and installation of furniture ongoing

Below Grade Activity / W. 131st Street Utilities

  • Punchlist work

Open Spaces between 130th and 131st Streets and along 12th Avenue

  • Continuation of living roof layer
  • Installation of electrical conduit, cobblestone, and trench drain
  • Hanover pavers/hardscape is ongoing
  • Installation of furnishings, drinking fountains, and other fixtures
  • Sidewalk, street lights, and street work
  • Testing of water feature systems has commenced
  • Testing of systems is underway

600 W. 125th Street

  • Drilling and installation of caissons
  • Excavation and test pit work along the south perimeter
  • Soil removal from construction site
  • Excavation, timber lagging, and excavation bracing is ongoing

 

Please note that all activities are subject to change based on weather and other field conditions.

 

What to Expect

Construction Activity

  • Regular weekday work hours: 7:00 a.m. to 6:00 p.m. Saturday and Sunday work hours: 7:00 a.m. to 5:00 p.m. After-hours permit issued for 6:00 a.m. construction start to allow for physical distancing for workers upon entry to the site.  After-hours permit issued for 6:00 p.m. to 11:00 p.m. Monday through Friday for exterior wall installation to be performed at the Business School buildings.
  • Material deliveries to site is ongoing

Temporary Traffic and Transportation Impacts

  • Refer to street signage for the west side of Broadway from 129th to 130th Streets -- parking is allowed after 6:00 p.m. and on weekends
  • W. 131st Street between Broadway and 12th Avenue is open for one-way westbound traffic
  • The parking lane will be closed on the south side of W. 125th Street from Broadway to St. Clair Place.  Parking will not be available on the south side of W. 125th Street from Broadway to the mid-block in front of the entire length of the 600 W. 125th Street construction fence.