Site at 125th Street and 12th Avenue
- Demolition of existing slab on grade on the west part of the site. Work may cause some noise and vibrations.
- Grading of the site to meet new elevations.
- Installation of underground stormwater concrete structures and piping.
- Trenching for new light poles.
- Trucking soil and concrete debris off-site to disposal facilities.
- Integrated pest control sitewide
-Please note that all activities are subject to change based on weather and other field conditions-