What is Happening
Due to inclement weather, the crane pick originally planned for December 27-28 has been rescheduled to January 3-4, pending necessary approvals. This work will require a full closure of West 131st Street (between Broadway and 12th Avenue) on Saturday, January 3 and Sunday, January 4 from 7:00 a.m. to 4:00 p.m. to load materials onto the roof of the Studebaker Building. West 131st Street is anticipated to reopen on Sunday, January 4 at approximately 4:00 p.m. after the crane has been dismantled.
Please note that all activities are subject to change based on weather and other field conditions.