Site at 125th Street and 12th Avenue

  • Importing clean fill and topsoil then compaction to grade the site to meet new elevations at west portion of the site
  • Pouring concrete at new sidewalk at 125th Street
  • Demolition, excavation, and off-loading soil offsite at west portion of the site
  • Completing the western stormwater gallery and inspection by the NYC Department of Buildings 
  • The installation of the new site perimeter fence is ongoing
  • Installation of new light pole bases and pulling cables
  • Installation of irrigation system piping 

-Please note that all activities are subject to change based on weather and other field conditions-

 


What to Expect

  • Work hours are 7:00 a.m. to 4:30 p.m., Monday to Friday; and 7:00 a.m. to 4:00 p.m. on Saturday. 
  • Work will not take place on Thursday, November 26 to Saturday, November 28 in observance of Thanksgiving weekend.
  • Expect noise, vibrations, odors, delivery of materials, and other impacts typically associated with construction projects.